Takeoff and the waste factor

What you'll learn

Turn a clean calculator number into what you actually buy — with the waste factor that keeps you from a second trip.

A calculator gives you an exact number. A jobsite never is. The gap between the two has a name — waste — and forgetting it is what sends you back to the supplier mid-pour.

Why the exact number is always short

Material gets lost on the way into the work: concrete left in the truck and the wheelbarrow, drywall offcuts around windows, tile that breaks, a board with a bad end. None of it ends up in the job, but all of it leaves your truck.

So every takeoff has two numbers: the net quantity the tool calculates, and the gross quantity you actually buy.

The waste factor

You add a percentage on top of net to cover the loss. Typical allowances:

  • Concrete: 5–10%
  • Drywall and lumber: 10–15%
  • Tile, simple layout: 10% — diagonal or lots of cuts: 15–20%

A 33.3 ft³ slab at 10% waste: 33.3 × 1.10 = 36.6 ft³ to order.

Then round to what you can actually buy

You don't buy 36.6 cubic feet — you buy whole bags, whole yards, whole sheets. Always round up to the purchase unit:

  • 36.6 ft³ ÷ 0.60 ft³ per bag = 61 bags → buy 61 (there's no 0.6 of a bag)
  • 36.6 ÷ 27 = 1.36 yd³ of ready-mix → order 1.5 yd³ (most plants sell in quarter- or half-yard steps)

Order short and the whole crew waits while someone drives for one more bag. Build the waste in, round up, and the job keeps moving.

Check your understanding

Question 1 of 1

Your slab calculator says you need exactly 40 bags of concrete. How many should you order?